Project Overview
The scope of this project included conducting an inflow and infiltration evaluation of the entire collection system and all pump stations, preparing a preliminary engineering report, designing the recommended improvements, preparing all bid documentation and construction management services. The project consisted of sewer line rehabilitation, sewer line extensions, force main upgrades, pump station upgrades, and upgrades to two wastewater treatment plants.
Construction Services
We upgraded 16 pump stations, constructed 16 new pump stations, and upgraded 2 treatment plants.
We also designed and provided construction oversight for several lines which provided new service to residents in the area. Thrasher has worked consistently with Pea Ridge PSD on a variety of projects including:
- Upgrades pump stations and electrical systems
- Saved client money in electrical costs
- Successful implementation of trench-less technology
- WWTP upgrades