Mingo County PSD Regional Water System

Water Treatment Plant

This project consisted of the design and construction of a new 2.0 MGD (expandable to 3.0 MGD) water treatment plant along the Tug Fork River in Naugatuck, WV. The design of the plant included:

  • Raw Water Intake Screens and Pump Station – Tug Fork (with potassium permanganate feed)
  • Static Mixer/Chemical Feed Room – Delpac 2020, PAC to second stage of flocculator, polymer, soda ash (pH adjustment if necessary)
  • Enhanced Coagulation/Flocculation – three stage flocculation with axial flow propeller mixers and variable frequency drives
  • Sedimentation – Four hour retention time, chain and flight sludge collectors, and sludge screw conveyors
  • Filtration – Four Roberts™ dual media filters, air/water simultaneous backwash, dynamic probes for evaluation of bed expansion to reduce mudball formation
  • SCADA System – WTP – all operating equipment monitoring and alarms, sixteen (16) water storage tanks and fourteen (14) booster stations, (flow, suction/discharge pressures, and alarms)
3,260,000

Gallon Water Storage Tanks (3)

2,100,000

Gallon Water Storage Tanks (2)

170,000

Gallon Water Storage Tank (1)

This project was awarded a WV ACEC Silver Award for Engineering Excellence.

Project Highlights

  • 70 miles of water distribution lines
  • 2 hydro-pneumatic pump stations
  • 6 booster stations
  • (3) 260,000 gallon water storage tanks
  • (2) 100,000 gallon water storage tanks
  • (1) 70,000 gallon water storage tank